this week we worked on creating a jig that would effectively, quickly, and accurately fit the two pieces for welding together to speed up the welding process. We have welded three total corners, but since it is so time-consuming, we might need to buy some aluminum adhesive for the top guideway to the top of the L-bracket. We completed Gantt chart and worked on paper and presentation. We also 3D printed more U-brackets, which we should be done with by the following week - needed to help 3D print some stuff for Ernest from the Bogie team. Also, completed collar design for solar mount with the third picture showing how the three legs will be attached. Fourth picture shows the collar from a different angle.